CS615 Quiz 2 Fall 2020

CS615 Quiz 2 Fall 2020

Quiz File 1

 

Question No 1

All of the following are the High level WBS structure tasks in Documentation tasks except:

Ordering procedure (Page 281)

Question No 2

_______________is also not a mandatory management task in high level management WBS tasks.

Customer interface  (Page 282)

Question No 3

_____________ will assemble larger work packages that can be appropriately managed and controlled.

Larger projects (Page 246)

Question No 4

The Delphi technique is a _____________estimation technique.

Human-based (Page 237)

Question No 5

All of the following are the High level WBS structure tasks in Training / Procurement tasks except:

Configuration management (Page 281)

Question No 6

The decomposition of a software project is one of the first tasks of…

Software project manager (Page 264)

Question No 7

COCOMO stands for _____________________.

Constructive Cost Model (Page 228)

 

 

Question No 8

Which of the following guidline for creating the software project schedule is used to group similar tasks and activities so that they are completed successfully.

Classification (Page 288)

 

Question No 9

Estimating the effort in the basic COCOMO technique involves following three steps except:

Calculating the effort adjustment factor (Page 233)

Question No 10

Functional decomposition of a software project is a division of the system into

Operational components (Page 267)

Quiz File 2

Question No 1

Which of the following guidline for creating the software project schedule is used to group similar tasks and activities so that they are completed successfully.

Classification (Page 288)

Question No 2

Estimating the effort in the basic COCOMO technique involves following three steps except:

Calculating the effort adjustment factor (Page 233)

Question No 3

Software project ……………is an activity that distributes estimated effort across the planned project duration by allocating the effort to specific software engineering tasks.

Scheduling (Page 284)

Question No 4

A node on a network schedule is that point in time at which an activity —————-.

Begins or Ends (Page 297)

Question No 5

Predecessor activities need to ———— before the next can begin. After a predecessor activity is completed, the successor activity becomes the predecessor for another activity.

End (Page 297)

Question No 6

Which of the following is displayed as an S-curve?

Critical path

 

Question No 7

Which of the following reason is more important to be handled to prevent project delay

Unrealistic initial deadline (Page 286)

Question No 8

___________________is not a mandatory management task in high level management WBS tasks.

Risk analysis and risk management

Question No 9

If the tasks are not organized efficiently, it becomes difficult to schedule and allocate _________________to the tasks.

Resources (Page 273)

Question No 10

All of the following are the High level WBS structure tasks in Documentation tasks except:

Administration and services (Page 281)